ROAD FORTIFICATION
Special Hillside Issue
|
CASE STUDY
The road had begun to slip down the hillside and was falling apart with large cracks. Avalon fortified the road with drilled reinforced concrete piers, helical tiebacks and a reinforced concrete wall.
Design Engineer:Bob Patterson, Patterson & Associates.
|
|
In this picture, Avalon is lowering reinforcing steel into deep drilled holes which will be poured with concrete to form drilled piers.
|
|
Here is a row of drilled piers ready for concrete.
|
|
Tiebacks are installed to grip deep into the hillside, for lateral support.
|
|
The rim of the fortification is ready to be poured, firmly attaching the drilled piers to the tiebacks.
|
|
The road is now stable; the road fortification is complete.
The edge of the road is now supported vertically with drilled piers, and the entire width of the road is supported laterally by helical tiebacks.
|
|
Avalon Structural, Inc. 181 Ridgeview Drive Aptos, CA 95003 (831) 479-4389 (office) info@avalonstructural.com |
Copyright © 2015 Avalon Structural, Inc. All Rights Reserved
|
CA License 677116 Classifications: B, C-8 Avalon is a general building contracting firm and does not employ engineers. |
|
|
|